5.1.1.
Formål
Kontraktens hovedformål: Bygge- og anlægsarbejder
Primær klassifikation (cpv): 45314310 Kabellægningsarbejder
Supplerende klassifikation (cpv): 76520000 Offshoreaktiviteter
5.1.2.
Udførelsessted
Land: Danmark
Hvor som helst i det pågældende land
Yderligere oplysninger: reinvestment of an existing 400-kV cable system of three single-core cables between Sweden and Den-mark, connecting the transition stations of Skibstrupgaard (SKB) in Denmark and Kristinelund (KLD) in Sweden.
5.1.4.
Fornyelse
Højeste antal fornyelser: 0
5.1.6.
Generelle oplysninger
Indkøbsprojekt, der ikke finansieres med EU-midler
Udbuddet er omfattet af aftalen om offentlige udbud (GPA): ja
5.1.15.
Teknikker
Rammeaftale:
Ingen rammeaftale
Oplysninger om det dynamiske indkøbssystem:
Intet dynamisk indkøbssystem
5.1.16.
Yderligere oplysninger, mægling og gennemgang
Organisation med ansvar for klager: Klagenævnet for Udbud
Oplysninger om klagefrister: Complaints regarding a candidate not being prequalified must be filed with The Complaints Board for Public Procurement within 20 calendar days starting the day after the contracting authority has sent notification to the candidates involved, provided that the notification includes a short account of the relevant reasons for the decision. Other complaints must be filed with The Complaints Board for Public Procurement within: 1. 45 calendar days after the contracting authority has published a contract award notice in the Official Journal of the European Union (with effect from the day following the publication date); 2. 30 calendar days starting the day after the contracting authority has informed the tenderers in question, that the contracting authority has entered into a contract based on a framework agreement through reopening of competition or a dynamic purchasing system, provided that the notification includes a short account of the relevant reasons for the decision. 3. 6 months starting the day after the contracting authority has sent notification to the candidates/tenderers involved that the contracting authority has entered into the framework agreement, provided that the notification included a short account of the relevant reasons for the decision.
Organisation, der leverer supplerende oplysninger om udbudsproceduren: Energinet Eltransmission A/S
Organisation, der sikrer adgang til udbudsdokumenterne offline: Energinet Eltransmission A/S
Organisation, der leverer yderligere oplysninger om klageprocedurerne: Konkurrence- og Forbrugerstyrelsen
Organisation, hvis budget anvendes til at betale for kontrakten: Energinet Eltransmission A/S
Organisation, der udfører betalingen: Energinet Eltransmission A/S
Organisation, der underskriver kontrakten: Energinet Eltransmission A/S
TED eSender: Mercell Holding ASA