« Tilbage til oversigten over alle licitationer


104/2025
354773-2025 - Planlægning
Danmark – Bygge- og anlægsarbejder – Market Dialogue - 3 GW Offshore Wind Farms - Denmark
OJ S 104/2025 02/06/2025
Forhåndsmeddelelse eller vejledende periodisk bekendtgørelse, der kun er anvendt til informationsformål
Bygge og anlæg
1. Køber
1.1.
Køber
Officielt navnDanish Energy Agency
Køberens retlige statusCentral regeringsmyndighed
Den ordregivende myndigheds aktivitetGenerelle offentlige tjenesteydelser
2. Procedure
2.1.
Procedure
TitelMarket Dialogue - 3 GW Offshore Wind Farms - Denmark
BeskrivelseThe Danish Energy Agency (DEA) invites potential tenderers and relevant economic operators to participate in the market dialogue regarding the procurement procedures of 3 GW Offshore Wind Farms – Denmark. The draft procurement material of the upcoming procurement procedures of 3 GW Offshore Wind Farms is largely based upon the procurement material of the procurement procedures of 6 GW Offshore Wind Farms, where the three (3) North Sea I areas received no bids in December 2024. Since December thorough new analyses have been made based upon dialogues with the market in December 2024 and January 2025 to support the political decision to determine which changes could be made to the procurement procedures to ensure market participation in a potential retender. Pursuant to the political agreement about the retender, dated 19. May 2025, the original procurement procedures have been amended to reflect changes, i.e. to the amount of sites tendered out simultaneously and the timeline, both regarding the procurement process and the construction process of the offshore wind farm, the minimum requirements for eligibility, the payment structure, constituting subsidy through a capability-based Contract for Difference (CfD), and the sanction regime.Pursuant to the political agreement about the retender, dated 19. May 2025, the original procurement procedures have been amended to reflect changes, i.e. for example to the amount of sites tendered out simultaneously and the timeline, both regarding the procurement process and the construction process of the offshore wind farm, the minimum requirements for eligibility, the payment structure, constituting subsidy through a capability-based Contract for Difference (CfD), and the sanction regime. The market dialogue will be initiated in two steps. The first step concerns a report regarding the proposed method for collecting relevant data and estimating potential production in a capability-based two-way Contract for Difference (CfD) scheme, which will apply in the new procurement procedures of 3 GW Offshore Wind Farms. The report is accompanied by a questionnaire for the participants in the market dialogue. Both the report and the questionnaire will be published by the DEA in EU-Supply, simultaneously with the initiation of the market dialogue. The second step of the market dialogue concerns the draft procurement material as a whole, and it will be initiated by the DEA through the "Messages"-module in EU Supply. The second step of the market dialogue will be conducted expectedly during June/July-August. When the second step of the market dialogue is initiated, the DEA expects to publish all documents of the procurement material. However, if deemed necessary by the DEA, the DEA reserves the right to publish specific documents of the procurement material after the second step of the market dialogue is initiated. All new material published through EU-Supply will be announced to all participants through the "Messages"-module as they are published. Potential tenderers and relevant economic operators who wish to participate in the market dialogue should hence sign up in EU-Supply. Participation in both or either steps of the market dialogue is not a prerequisite for participation in the market dialogue as a whole and potential tenderers and relevant economic operators are therefore welcome to provide input only to the initially published material regarding the proposed method for collecting relevant data and estimating potential production in a capability-based two-way CfD or to the subsequent draft procurement material or to both sets of material. A public consultation regarding certain State aid law aspects will be conducted simultaneously with the second step of the market dialogue, and will also be conducted through EU-Supply. For further information regarding the procedure of the market dialogue, reference is made to the descriptions under section "Additional information" in the category "Further Information".
Intern ID2025-1835
2.1.1.
Formål
Kontraktens hovedformålBygge og anlæg
Primær klassifikation (cpv): 45000000 Bygge- og anlægsarbejder
Supplerende klassifikation (cpv): 31121320 Vindturbiner, 31121330 Vindturbinegeneratorer, 31121340 Vindmøllepark, 31160000 Dele til elektriske motorer, generatorer og transformatorer, 31170000 Transformatorer, 31213400 Distributionssystem, 31300000 Isolerede ledninger og kabler, 45244000 Arbejder til havs, 45244100 Havanlæg
2.1.2.
Udførelsessted
Landsdel (NUTS)Vestjylland (DK041)
LandDanmark
Yderligere oplysningerThe location sites of the offshore wind farms is in North Sea I, Mid, North Sea I, South, and Hesselø, and the exact locations will be further specified in the procurement documents.
2.1.4.
Generelle oplysninger
Yderligere oplysningerThe initial step of the market dialogue concerning the proposed method for collecting relevant data and estimating potential production in a capability-based two-way CfD is based on a report, Estimation of Available Active Power for Two-Way Contract for Difference in Offshore Wind Energy Application, available in EU-supply. The market dialogue will be carried out primarily in writing in accordance with the specifications presented in the document, Invitation to market dialogue about 3 GW Offshore Wind Farm. However, the first step of the market dialogue will include an information meeting regarding the method for collecting relevant data and estimating potential production under a capability-based two-way CfD. The module, “Messages”, in EU-Supply, shall be used to attach and submit the inputs from the participants. The participants in the market dialogue are invited to submit answers as soon as possible to the questionnaire regarding the report containing the proposed method for collecting relevant data and estimating potential production in a capability-based two-way CfD, as the inputs received are most valuable and will be used for the further development of the method supporting the subsidy scheme. The second step in the market dialogue concerns the draft procurement material as a whole, and it will be initiated by the DEA through the "Messages"-module in EU Supply. The second step of the market dialogue will be conducted expectedly during June/July-August, and the draft procurement material will be uploaded to EU-Supply, when the second step is initiated. A public consultation with a questionnaire regarding the DEA’s main assumptions and considerations regarding the state aid's impact on competition and the proportionality of the aid, will be conducted simultaneously with the second step of the market dialogue. This public consultation fulfils the obligation for the DEA according to section 4.1.3.4 of the CEEAG and will be open for inputs during the required six (6) weeks. The participants in the market dialogue are invited to submit their written inputs to the DEA regarding both the first step and the second step of the market dialogue at the latest on 6. August 2025. As part of the finalization of the procurement documents for the upcoming procurement procedures the Danish Energy Agency is currently still assessing the appropriate legal basis for the procurement procedures. It is however the expectation of the Danish Energy Agency that the procurement procedures will be conducted according to Directive 2014/24/EU, implemented into Danish Law by the Danish Public Procurement Act, statutory order (LBK) no. 116 of 03/02/2025. All communication during the market dialogue will take place via EU-Supply.
Retsgrundlag
Direktiv 2014/24/EU
http://data.europa.eu/eli/dir/2014/24/oj - As part of the finalisation of the procurement documents for the upcoming procurement procedures the Danish Energy Agency is currently still assessing the appropriate legal basis for the procurement procedures. It is however the expectation of the Danish Energy Agency that the procurement procedures will be conducted according to Directive 2014/24/EU, implemented into Danish Law.
3. Del
3.1.
Teknisk ID for delenPAR-0000
TitelMarket Dialogue - 3 GW Offshore Wind Farms - Denmark
BeskrivelseThe Danish Energy Agency (DEA) invites potential tenderers and relevant economic operators to participate in the market dialogue regarding the procurement procedures of 3 GW Offshore Wind Farms – Denmark. The draft procurement material of the upcoming procurement procedures of 3 GW Offshore Wind Farms is largely based upon the procurement material of the procurement procedures of 6 GW Offshore Wind Farms, where the three (3) North Sea I areas received no bids in December 2024. Since December thorough new analyses have been made based upon dialogues with the market in December 2024 and January 2025 to support the political decision to determine which changes could be made to the procurement procedures to ensure market participation in a potential retender. Pursuant to the political agreement about the retender, dated 19. May 2025, the original procurement procedures have been amended to reflect changes, i.e. to the amount of sites tendered out simultaneously and the timeline, both regarding the procurement process and the construction process of the offshore wind farm, the minimum requirements for eligibility, the payment structure, constituting subsidy through a capability-based Contract for Difference (CfD), and the sanction regime.Pursuant to the political agreement about the retender, dated 19. May 2025, the original procurement procedures have been amended to reflect changes, i.e. for example to the amount of sites tendered out simultaneously and the timeline, both regarding the procurement process and the construction process of the offshore wind farm, the minimum requirements for eligibility, the payment structure, constituting subsidy through a capability-based Contract for Difference (CfD), and the sanction regime. The market dialogue will be initiated in two steps. The first step concerns a report regarding the proposed method for collecting relevant data and estimating potential production in a capability-based two-way Contract for Difference (CfD) scheme, which will apply in the new procurement procedures of 3 GW Offshore Wind Farms. The report is accompanied by a questionnaire for the participants in the market dialogue. Both the report and the questionnaire will be published by the DEA in EU-Supply, simultaneously with the initiation of the market dialogue. The second step of the market dialogue concerns the draft procurement material as a whole, and it will be initiated by the DEA through the "Messages"-module in EU Supply. The second step of the market dialogue will be conducted expectedly during June/July-August. When the second step of the market dialogue is initiated, the DEA expects to publish all documents of the procurement material. However, if deemed necessary by the DEA, the DEA reserves the right to publish specific documents of the procurement material after the second step of the market dialogue is initiated. All new material published through EU-Supply will be announced to all participants through the "Messages"-module as they are published. Potential tenderers and relevant economic operators who wish to participate in the market dialogue should hence sign up in EU-Supply. Participation in both or either steps of the market dialogue is not a prerequisite for participation in the market dialogue as a whole and potential tenderers and relevant economic operators are therefore welcome to provide input only to the initially published material regarding the proposed method for collecting relevant data and estimating potential production in a capability-based two-way CfD or to the subsequent draft procurement material or to both sets of material. A public consultation regarding certain State aid law aspects will be conducted simultaneously with the second step of the market dialogue, and will also be conducted through EU-Supply. For further information regarding the procedure of the market dialogue, reference is made to the descriptions under section "Additional information" in the category "Further Information".
Intern ID2025-1835
3.1.1.
Formål
Kontraktens hovedformålBygge og anlæg
Primær klassifikation (cpv): 45000000 Bygge- og anlægsarbejder
Supplerende klassifikation (cpv): 31121320 Vindturbiner
Supplerende klassifikation (cpv): 31121330 Vindturbinegeneratorer
Supplerende klassifikation (cpv): 31121340 Vindmøllepark
Supplerende klassifikation (cpv): 31160000 Dele til elektriske motorer, generatorer og transformatorer
Supplerende klassifikation (cpv): 31170000 Transformatorer
Supplerende klassifikation (cpv): 31213400 Distributionssystem
Supplerende klassifikation (cpv): 31300000 Isolerede ledninger og kabler
Supplerende klassifikation (cpv): 45244000 Arbejder til havs
Supplerende klassifikation (cpv): 45244100 Havanlæg
3.1.2.
Udførelsessted
Landsdel (NUTS)Nordsjælland (DK013)
LandDanmark
3.1.5.
Generelle oplysninger
Yderligere oplysningerThe initial step of the market dialogue concerning the proposed method for collecting relevant data and estimating potential production in a capability-based two-way CfD is based on a report, Estimation of Available Active Power for Two-Way Contract for Difference in Offshore Wind Energy Application, available in EU-supply. The market dialogue will be carried out primarily in writing in accordance with the specifications presented in the document, Invitation to market dialogue about 3 GW Offshore Wind Farm. However, the first step of the market dialogue will include an information meeting regarding the method for collecting relevant data and estimating potential production under a capability-based two-way CfD. The module, “Messages”, in EU-Supply, shall be used to attach and submit the inputs from the participants. The participants in the market dialogue are invited to submit answers as soon as possible to the questionnaire regarding the report containing the proposed method for collecting relevant data and estimating potential production in a capability-based two-way CfD, as the inputs received are most valuable and will be used for the further development of the method supporting the subsidy scheme. The second step in the market dialogue concerns the draft procurement material as a whole, and it will be initiated by the DEA through the "Messages"-module in EU Supply. The second step of the market dialogue will be conducted expectedly during June/July-August, and the draft procurement material will be uploaded to EU-Supply, when the second step is initiated. A public consultation with a questionnaire regarding the DEA’s main assumptions and considerations regarding the state aid's impact on competition and the proportionality of the aid, will be conducted simultaneously with the second step of the market dialogue. This public consultation fulfils the obligation for the DEA according to section 4.1.3.4 of the CEEAG and will be open for inputs during the required six (6) weeks. The participants in the market dialogue are invited to submit their written inputs to the DEA regarding both the first step and the second step of the market dialogue at the latest on 6. August 2025. As part of the finalization of the procurement documents for the upcoming procurement procedures the Danish Energy Agency is currently still assessing the appropriate legal basis for the procurement procedures. It is however the expectation of the Danish Energy Agency that the procurement procedures will be conducted according to Directive 2014/24/EU, implemented into Danish Law by the Danish Public Procurement Act, statutory order (LBK) no. 116 of 03/02/2025. All communication during the market dialogue will take place via EU-Supply.
3.1.6.
Udbudsdokumenter
3.1.9.
Yderligere oplysninger, mægling og gennemgang
Organisation med ansvar for klagerKlagenævnet for Udbud
Organisation, der leverer yderligere oplysninger om klageprocedurerneKonkurrence- og Forbrugerstyrelsen
8. Organisationer
8.1.
ORG-0001
Officielt navnDanish Energy Agency
RegistreringsnummerDanish Energy Agency
PostadresseCarsten Niebuhrs Gade 43
ByKøbenhavn V
Postnummer1577
Landsdel (NUTS)Byen København (DK011)
LandDanmark
EnhedCamilla Juel Irmark
Telefon+45 33 92 23 47
Denne organisations roller
Køber
8.1.
ORG-0002
Officielt navnKlagenævnet for Udbud
Registreringsnummer37795526
PostadresseNævnenes Hus, Toldboden 2
ByViborg
Postnummer8800
Landsdel (NUTS)Vestjylland (DK041)
LandDanmark
Telefon+45 72405600
Internetadressehttps://klfu.naevneneshus.dk/
Denne organisations roller
Organisation med ansvar for klager
8.1.
ORG-0003
Officielt navnKonkurrence- og Forbrugerstyrelsen
Registreringsnummer10294819
PostadresseCarl Jacobsens Vej 35
ByValby
Postnummer2500
Landsdel (NUTS)Byen København (DK011)
LandDanmark
E-mailkfst@kfst.dk
Telefon+45 41715000
Internetadressehttp://www.kfst.dk
Denne organisations roller
Organisation, der leverer yderligere oplysninger om klageprocedurerne
8.1.
ORG-0004
Officielt navnMercell Holding ASA
Registreringsnummer980921565
PostadresseAskekroken 11
ByOslo
Postnummer0277
Landsdel (NUTS)Oslo (NO081)
LandNorge
EnhedeSender
Telefon+47 21018800
Fax+47 21018801
Internetadressehttp://mercell.com/
Denne organisations roller
TED eSender
Oplysninger om bekendtgørelsen
Bekendtgørelsens ID652efbec-2be1-4026-8216-fb67d11f1736  -  01
FormulartypePlanlægning
BekendtgørelsestypeForhåndsmeddelelse eller vejledende periodisk bekendtgørelse, der kun er anvendt til informationsformål
Bekendtgørelsesundertype4
Afsendelsesdato for bekendtgørelsen28/05/2025 13:28:44 (UTC+00:00) vesteuropæisk tid, GMT
Dato for afsendelse af bekendtgørelsen (eSender)28/05/2025 15:01:16 (UTC+00:00) vesteuropæisk tid, GMT
Bekendtgørelsens officielle sprogengelsk
Bekendtgørelsesnummer354773-2025
EUT-S-nummer104/2025
Offentliggørelsesdato02/06/2025
Den påtænkte dato for offentliggørelse af en udbudsbekendtgørelse inden for denne procedure01/10/2025

« Tilbage til oversigten over alle licitationer